<< Click to Display Table of Contents >> Navigation: Modules > Manufacturing > Planning > Production Schedule View |
Overview
This application shows the Gantt chart (as displayed in production planning) as a standalone.
Function
When the application is opened you will view the following screen:
Here you can view a schematic of where in the month the ticket is scheduled as well as which asset/machine it is scheduled for.
When you edit a ticket, this schedule will be updated with the new information for the ticket or when you close a ticket subsequent tickets will be moved earlier.
Weekends are excluded when scheduling tickets unless specified otherwise.
Paused tickets will be displayed in gray: .
Right click on the grid for more options:
Changes made to this application will be updated in the production planning application and changes made in the production planning application will be updated in this applicaion.